Project Description

South West College

Mc Mackin Contracts are currently carrying out all siteworks on a new School in Enniskillen, Co. Fermanagh for Tracey Bros.

The Project involved excavation of approx. 15,000m³ including disposal off-site.
Works involve construction of a new Roads, Car Parks, foundations, floors etc as well as temporary car parks. Earthworks included extraction of approx. 10,000m³ of rock and reinforced concrete slabs, place and compact as part of the road make-up. There was also approx. 10,000m³ of clay excavated and hauled to nearby tips off-site.

Works also included:

  • All drainage works including manholes, testing and commissioning
  • Diversion of existing services
  • Construction of new roads leaving ready for tarmac
  • Construction of concrete footpaths, kerbing etc
  • Works included the construction of ancillary chambers, testing & commissioning
  • Re-alignment and construction of service roads
  • Crushing on-site of rock on-site and placing material
  • Demolition of existing building/structures

Project Details

CLIENT

Tracey Bros

CONTRACT PERIOD

August 2018 – June 2020

PROJECT VALUE

£0.85 Million

LOCATION

Enniskillen, Co Fermanagh