Smooth Point Pier
McMackin Contracts package includes breaking out existing concrete slab to pier, pulverising concrete to separate the rebar and concrete, crushing concrete, grading concrete for reuse as recycled aggregate within the works. This reduces waste to landfill and reduces the number of slow haulage movements in and around the docks. Bulk excavation works and excavation to expose pier wall.
Project Details
CLIENT
ABCO Marine
Contract Period
Dec 2019 – Current
PROJECT VALUE
€175K
LOCATION
Killybegs, Co Donegal