Project Description

Navan Town Scheme 2030

The project on Railway St consisted of the following:

• Removal of Existing Carriageway (approx. 170m)
• Install new 225mm Dia SDR17 PE Watermain
• Install new 110mm Dia Traffic, Broadband and Virgin Ducting
• Install new 160mm ESB Ducting
• Removal of Existing Footpaths
• Install new Footpaths (up to sub-screed level)
• Install Hippo Road Gullies
• Decommissioning Works on 5” Ductile Iron Main
• Decommissioning works on 225mm Dia Asbestos Main
• Live Connections to 250mm Dia HDPE water main
• Live Connections to Foul Drainage
• Live Connections to Surface Water Drainage

This project consisted of a bulk Reduced level dig on the existing carriage way. Once the removal of the existing carriageway was complete then the work commenced on the new 225 DIA SDR17 PE Water main. Due to the nature of the project the main had to be installed using Fusion Welded Couplers as opposed to butt fusion welding the segments of the main together. All welds on the couplers and saddles were carried out by McMackin Contracts. Upon the completion of the final welds a water pressure test was carried out, and it was found that there were no leaks on the main.

Various other services were installed down the centre of the carriageway. All excavation works were carried out by McMackin Contracts. The new road formation was then installed up to sub base level. The road was then formed up to binder level by Roadstone Tarmac. Work then commence in the footpaths. The old footpaths were removed, and replaced with the new design specification. Footpaths were then finished by Premier Paving.

Project Details

CLIENT

John Cradock Ltd

CONTRACT PERIOD

July 2019 – April 2020

PROJECT VALUE

€0.59 Million

LOCATION

Navan, Co. Meath

Project Gallery