Project Description

250kW Anaerobic Digestion Plant

Eglinton, Co. Derry

 

Client:  Evergreen Biogas Ltd

Value:  £640k

Contact:  Conor O’Driscoll – 074 0736 8010

Contract Period:  October 2016 – April 2017

 

McMackin Contracts were contracted to complete all concrete, siteworks and drainage on a new 250kW AD Plant in Eglinton, Co. Derry. The project comprised of a  300m2 portal frame workshop and adjoining two storey office facility, a large silage pit with in situ walls and structural concrete floor, three digester tanks and a large structural concrete yard area. The site was originally at various levels and required a cut/fill exercise with mixed ground conditions, mainly rock.

McMackin also installed all HDPE and ductile iron pipework underground and completed tank bases for three large digester tanks with the precast tank walls supplied by Macrete. Other works involved the following:

  1. 750m2 structural concrete yard;
  2. Installation of underground tanks for storm and “dirty”/unclean water;
  3. Excavation of drainage in rock areas;
  4. Backfilling submerged digester tanks including tanking;
  5. Kerbing around concrete areas;
  6. Fencing to boundary of site.

Eglinton 06 Eglinton 07 Eglinton 08 Eglinton 02 Eglinton 03 Eglinton 04 Eglinton 05